PROJECT UPDATE

UPDATE: 03.19.2020

CONSTRUCTION PROGRESS

Beginning next week, we will begin to shift traffic to the inside lanes against the median - one lane open in each direction.

​On Monday, March 23, the contractor will begin milling the roadway next to the sidewalks in preparation for the laying of the asphalt. This final paving will complete the roadway from Winona to the end of the job at Bertrand.

​Be sure you stay alert during this last phase of the project. 


WHAT TO EXPECT IN THE NEXT FEW WEEKS
With the onset of the nicer Spring weather, landscaping crews will be installing more plants and placing mulch.

The new signals will also be installed to replace the temporary signal assets we have been using to date.

On a side note - please make sure you are taking precautionary actions during the COVID-19 outbreak.   Click here to access resources the City of Knoxville has provided for the community. 

 

UPDATE: 02.05.2020

CONSTRUCTION PROGRESS

Over the last few weeks, our contractor has continued to make significant progress, even through rainy weather.

All concrete sidewalks and driveways are now completed. The new traffic signal arms have been placed and new traffic signal equipment has been completed at Bertrand. All street and pedestrian light poles are in place and all remaining benches, trash receptacles, and bike loops have been installed.


ONGOING WORK
The electricians are pulling traffic signal and fiber optic wires, in addition to wiring up the traffic control cabinets.


The final asphalt patchwork in the bike lane and behind the sidewalk at driveways is being placed.


Landscaping on the south side of Magnolia between Myrtle and Bertrand is being placed and readied for spring.


WHAT TO EXPECT IN THE NEXT FEW WEEKS
The final paving to occur from Winona to the end of the job (Bertrand) this Spring.


The new Stamped Crosswalks will be installed after final paving with warmer temperatures. (55 degrees and rising).

UPDATE: 12.10.2019

CONSTRUCTION PROGRESS

The $7 million Magnolia Avenue Streetscape Project is nearing completion. The first phase of the project is substantially complete, with work on second phase expected to be wrapped up by spring 2020.

The project includes landscaped center medians and left-turn lanes, street trees, wider sidewalks, bike lanes, safer and stamped crosswalks with pedestrian signals, and enhanced transit stops and shelters on Magnolia Avenue between Jessamine and North Bertrand streets.

Mayor Rogero, City Council members, City staff, TDOT staff, representatives of the project team and neighborhood stakeholders will cut a ribbon to celebrate the streetscape improvements on Dec. 12, 2019 at 10 a.m. near the intersection of Jessamine and Magnolia Avenue.

UPDATE: 10.22.2019

CONSTRUCTION PROGRESS

Progress on Magnolia Ave is coming along. Phase 1 from Jessamine St to Winona St has received final pavement.

 

Landscapers are installing shrubs and ground cover during the fall planting season. Final touches and clean-up will occur on Phase 1 over the next couple weeks.

 

The transition between phases near Myrtle St will be paved this fall when final paving occurs on Phase 2 to Bertrand St. Work on Phase 2 continues as a new storm system, lighting, traffic signals, curb and gutter, sidewalks, driveways, trees and other landscaping, bus stops, benches, and bicycle loops are being installed.

 

UPDATE: 09.04.2019

CONSTRUCTION PROGRESS

All sidewalks, colored concrete pads, curb and gutter, grade work in landscape areas, and asphalt work is complete on the north side. All pedestrian and street light poles are standing on the north side.

Demolition on the south side of Magnolia is in full swing.

Progression Electric will begin installing lighting and fiber optic conduit. Conner Excavation will begin storm water installation.

KUB looking at options for fire hydrant in front of Pellissippi State (across from Holly St) TVA Fair at Chilhowee Park September 6th - 15th

As Conner Excavation uncovers AT&T duct bank conflicts, Casey Tyree will work out storm water design.

 

UPDATE: 08.07.2019

CONSTRUCTION PROGRESS


McKinnon Construction has placed sidewalk from Bertrand to Austin, along with the curb and gutter at Austin and near PBS, and the median curb near this section.  The grading has been completed on the side streets and around the sidewalks and paving has occurred around the center median.  Three pedestrian light pole foundations have been poured with conduit in preparation for the wiring of the lights. Over the next two weeks expect to see more sidewalks, curb and gutter being placed, additional grade work, paving of side streets, and light pole base installations.

 

 

UPDATE: 07.18.2019

CONSTRUCTION PROGRESS

 

Work Completed Since Last Progress Meeting
Rogers Group curbs/island curbs complete. Trowel Trades to Winona. Southeast patched through Winona. Progression underground complete and started traffic signal poles (6 of 8 poles are up). VEC topsoil and mulch to Winona. SE patching complete except for islands.

 

 

TWO-WEEK LOOK AHEAD

Trowel Trades finishing sidewalks from Winona to Myrtle next week and colored concrete areas. SE to patch around the islands. Progression flying traffic signal arms Monday. 3 weeks after the arms flown all traffic signals should be working except for the ped poles, clam, and push buttons. Progression will have all pole foundations poured by next Friday except for 1 in conflict with existing light pole. Progress lighting crew will start putting up light poles next Tuesday and pulling wire. VEC working on planter areas after Trowel Trades finishes. Benches on the north side are almost all in place

 

UPDATE: 07.08.2019

CONSTRUCTION PROGRESS

Flaggers and traffic drums will be on Magnolia Avenue from Winona to Jessamine guiding traffic to allow additional work space for the streetscapes project. 

Curb and sidewalk work continues through to Myrtle, while concrete work through to Bertrand progresses. Topsoil, mulch and trees are being added and foundations for more light poles are going in as well. 

UPDATE: 06.10.2019

CONSTRUCTION PROGRESS

Roads currently closed: south side of Winona and Myrtle, Holly, Austin, north side of Bertrand.

 

Storm work is nearly complete along both phases of the Magnolia Streetscapes Project. Signal pole foundations are being poured, while curb and sidewalk work continues. Trees, topsoil and mulch are also going in along the south side of the street. 

UPDATE: 05.29.2019

CONSTRUCTION PROGRESS

Roads currently Closed: south side of Winona and Myrtle, Holly, Austin, north side of Bertrand.

 

All of the sidewalk on the north side has been completed except for a few pieces near Myrtle.
Curb work is completed up to Gibbons except for the radiuses at Jessamine. All storm installation is complete except for the south side at Myrtle.

Concrete work has begun on Phase II of the project. Traffic signal poles are going in along the south side of Jessamine and landscape works continues on the north side.

Underground utility work, curbs and sidewalk work continues. 

UPDATE: 05.14.2019

CONSTRUCTION PROGRESS

Road closure update: Austin Street at Magnolia will also be closed for a few weeks as storm work progresses along Magnolia. 

 

Concrete work has begun on Phase II of the project. Traffic signal poles are going in along the south side of Jessamine and landscape works continues on the north side.

Underground utility work, curbs and sidewalk work continues. 

UPDATE: 04.11.2019

CONSTRUCTION PROGRESS

Road closure update:  Gibbons Street will remain closed.

Work will begin on the South side of Magnolia Avenue while it is completed on the North side. Landscaping and storm work continues while street and pedestrian light poles are being installed. 

UPDATE: 03.30.2019

CONSTRUCTION PROGRESS

Road closure update:  Gibbons Street will remain closed.

Reminder: The Knoxville Covenant Marathon is Sunday, March 31, and the course crosses Magnolia. Be aware of runners!

Curb and gutter work has been completed on the north side of Magnolia Avenue. Sidewalks on the north side are about 75% complete, and bench and bus pads are being prepared. 

UPDATE: 03.25.2019

CONSTRUCTION PROGRESS

Road closure update:  Gibbons Street will remain closed.

 

Work on the south side of Magnolia should begin in the next few weeks. Curbs and gutters are in place to Winona. Sidewalk work continues, as well as asphalt patching. 

UPDATE: 02.28.2019

CONSTRUCTION PROGRESS

Road closure update:  Gibbons Street will remain closed.

 

Curb and sidewalk work continues, and traffic signal pole foundations are starting to be installed. The Magnolia Avenue monument is also beginning to be installed. 

UPDATE: 02.18.2019

CONSTRUCTION PROGRESS

Road closure update:  Gibbons Street will remain closed.

 

Storm work through Myrtle Street continues along Magnolia. Curbs from Jessamine through Winona are completed, and sidewalks through Gibbons are nearly complete.

UPDATE: 01.31.2019

CONSTRUCTION PROGRESS

Road closure update: Jessamine Street will remain closed between Frazier Street and Gibbons Street through Jan. 31. Gibbons Street will remain closed through Feb. 16.

 

Storm drainage work continues to progress. Curbs and gutters are done on both sides of Jessamine Street. Underground work is done up to Gibbons Street. 

UPDATE: 01.18.2019

CONSTRUCTION PROGRESS

Road closure update: Jessamine Street will remain closed between Frazier Street and Gibbons Street through Jan. 31. Gibbons Street will remain closed through Feb. 16.

 

The storm drainage system is in place past Gibbons Street. Crews have started pouring curbs and gutters at Jessamine Street. 

UPDATE: 12.18.2018

CONSTRUCTION PROGRESS

Road closure update: Jessamine Street will remain closed between Frazier Street and Gibbons Street through Jan. 16.

 

The new storm system is now complete from First Creek to Jessamine Street where the water quality unit is located and installed. The storm system will continue east along the north side of Magnolia Avenue. Crews are preparing to replace curb, lighting infrastructure and new sidewalks as they progress. Follow us on Facebook, Twitter, or Instagram. You can receive text updates by texting "Magnolia" to 313131 as well. 

UPDATE: 11.15.2018

CONSTRUCTION PROGRESS

Things are moving smoothly along Magnolia, but traffic closures are coming. Follow us on Facebook, Twitter, or Instagram. You can receive text updates by texting "Magnolia" to 313131 as well. 

UPDATE: 11.2.2018

CONSTRUCTION PROGRESS

You may have noticed a large hole on Magnolia Avenue -- this is a good thing! Crews have dug 25 feet down to tie in the new stormwater system. In the coming weeks, Jessamine Street will see a closure while a new water quality unit is installed. Text alerts will be sent out, along with updates to our Facebook and Twitter

UPDATE: 10.1.2018

CONSTRUCTION PROGRESS

It may seem like not much is happening right now, but that's because most of the work is happening underground. In the next two weeks, both underground and above ground utilities will be changing at the corner of Jessamine Street and Magnolia Avenue, leading the way for substantial progress for the project.  

UPDATE: 8.30.2018

CONSTRUCTION PROGRESS

We have started the storm sewer work at the west end of the project.  The first step was to do some subsurface investigation work to address some unknowns.  We have excavated and located the unknown utilities and are currently working with the conflicting utility owners to determine the best course of action.  

UPDATE: 8.9.2018

PHASE 1 BEGINS

Mayor Madeline Rogero, city staff, and stakeholders within the Magnolia Avenue Streetscape project officially broke ground on the project today...

 

[read more]

UPDATE: 7.13.2018

PROJECT OPEN HOUSE ON JULY 23

Join City staff along with Vaughn and Melton who is performing construction engineering and inspection services, and The Franklin Group, the general contractor ...

 

[read more]

UPDATE: 5.23.2017

MAGNOLIA AVENUE OPEN STREETS EVENT

Knoxville’s fourth Open Streets transformed a mile of Magnolia Avenue into an open arena for pedestrians, bicycles, skateboards, roller skates, puppies and puppets—but absolutely no automobiles...